advertisers

Construction to begin May 6 on NW corner of I-465 in Indianapolis

Last Updated on May 5, 2019 by cassnetwork

INDIANAPOLIS – Construction on the northwest quadrant of I-465 is scheduled to begin Monday, May 6.

The Indiana Department of Transportation is working this summer to repair the interstates after several harsh winters of various freeze and thaw cycles. 

Crews will start working on parts of I-465 in the northwest corner, between 56th Street and U.S. 31. 

Work will be complete near the end of October, weather permitting.

Segment 1

  • Mid-May to beginning of September 
  • I-465 NB & SB from 56th Street to 96th Street 
  • Work will be done weeknights and Saturdays from 8 p.m. to 6 a.m. in Northbound lanes and from 8 p.m. to 7 a.m. in Southbound lanes.
  • Crews will be milling and repaving in this area.
  • There will be various lane closures in both directions. At least one lane will be open in each direction, but both NB and SB lanes could be affected at the same time. 

Segment 2

  • Late July to end of October 
  • I-465 EB & WB from 96th Street to U.S. 31
  • Work will be done weeknights and Saturdays from 8 p.m. to 6 a.m. in Eastbound lanes and 8 p.m. to 7 a.m. in Westbound lanes.
  • Crews will be milling and repaving in this area.
  • There will be various lane closures in both directions. At least one lane will be open in each direction, but both EB and WB lanes could be affected at the same time. 

SOURCE: News release from Indiana Department of Transportation

Cass County Online